Operating Reactors in Pakistan
Reactor Province Type MWe net Construction start Commercial operation Planned close
Karachi 1 Sindh PHWR 125 1966 December 1972 2019
Chashma 1 Punjab PWR 300 1993 June 2000 2040
Chashma 2 Punjab PWR 300 2005 May 2011 2051
Chashma 3 Punjab PWE 315 May 2011 December 2016 2056
Total (4) 1040 operating
Karachi is also known as KANUPP, Chashma as CHASNUPP.
Enriched fuel for the PWRs is imported from China.
The 2005 Energy Security Plan included intention of lifting nuclear capacity to 8800 MWe, 900 MWe of this by 2015 and a further 1500 MWe by 2020. Projections included four further Chinese reactors of 300 MWe each and seven of 1000 MWe, all PWR. There were tentative plans for China to build two 1000 MWe PWR units at Karachi as KANUPP 2&3, but China then in 2007 deferred development of its CNP-1000 type which would have been the only one of that size able to be exported. Pakistan then turned its attention to building smaller units with higher local content. However, in 2013 China revived its 1000 MWe designs with export intent, and made overtures to Pakistan for the ACP1000 design, which became Hualong One – see below.
Chashma 3 and 4
In June 2008 the government announced plans to build units 3&4 at Chashma, each 320 MWe gross and largely financed by China. A further agreement for China's help with the project was signed in October 2008, and given prominence as a counter to the US-India agreement shortly preceding it.
In March 2009 China's SNERDI announced that it was proceeding with design of Chashma 3&4, with China Zhongyuan Engineering Corp (CZEC) as the general contractor and China Nuclear Industry No.5 Construction Company as installer. In April 2009, a design contract with SNERDI was signed, and the government said that it had approved the project at a cost of $2.37 billion, with $1.75 billion of this involving "a foreign exchange component". In March 2010 Pakistan announced that it had agreed the terms for Chashma 3&4, whereby China would provide 82% of the total US$ 1.912 billion financing as three 20-year low-interest loans. It would also provide fuel for the reactors’ lifetime nominally of 40 years.
The main construction contract was signed in June 2010, and the two 340 MWe CNP-300 (315 MWe net) units were to be completed in eight years. They will have a design life of 40 years and be under IAEA safeguards. Construction of unit 3 officially started at the end of May 2011, and unit 4 in December 2011. Early in 2014 PAEC said they were several months ahead of schedule. In 2015 CZEC said completion of unit 3 would be in 2016, and in fact it was grid-connected in October, with full power and commercial operation in December. Unit 4 is expected to be grid connected by mid-2017.
The Nuclear Suppliers Group (NSG) has raised some questions about China's supply of Chasma 3&4. Contracts for units 1&2 were signed in 1990 and 2000 respectively, before 2004 when China joined the NSG, which maintains an embargo on sales of nuclear equipment to Pakistan. China argued that units 3&4 are similarly "grandfathered", and arrangements are consistent with those for units 1&2.
Chashma 5
In November 2010 the PAEC is reported to have signed a construction agreement with China National Nuclear Corporation (CNNC) for a fifth unit at Chashma. In February 2013 a further agreement was signed by PAEC with CNNC for a 1000 MWe unit at Chashma. It was reported that China expected that this deal would be controversial under the NPT and guidelines of the NSG. Early in 2013 CNNC confirmed its intention to build a 1000 MWe class reactor, and said it would be an ACP1000 unit, though not necessarily at Chashma. The status of any continuing plan for Chashma 5 is very uncertain, and it may have been displaced by plans for a plant near Multan in southwest Punjab. Certainly it has been overtaken by the Karachi Coastal project.
Karachi Coastal power project, K2 and K3
In June 2013 the Planning Commission said that two CNNC 1000 MWe class reactors would be used for Karachi 2 and 3 (KANUPP 2&3) near Karachi unit 1. Two coastal sites had been under consideration for the twin 1100 MWe units. CNNC in April 2013 announced an export agreement for the ACP1000, nominally 1100 MWe, apparently for Pakistan. This was confirmed in June by the PAEC which said that the next nuclear project would be 1100 MWe class units which it would build, the Karachi Coastal Power station.
In July 2013 ECNEC approved two units of the Karachi Costal Power Project with net generation capacity of 2,117 MWe. The total cost of this was estimated at Rs 959 billion ($9.595 billion), with $6.5 billion (68%) being vendor finance. PAEC also said that 82% of the total cost would be financed by China. At the end of August 2013 contracts were signed in Shanghai with CNNC, China Zhongyuan Engineering Co. Ltd. (CZEC), China Nuclear Power Engineering Co. Ltd. (CNPE), Nuclear Power Institute of China (NPIC), and East China Electric Power Designing Institute (ECEPDI). Ground breaking at the site near Paradise Point, 25 km west of Karachi, took place in November 2013, but in October 2014 the Sindh high court ruling stopped site work following a challenge on environmental grounds, and the restraining order was extended to early December. The project was re-launched in August 2015, and construction of the first unit started then.
The Pakistan Nuclear Regulatory Authority received the safety analysis of China’s ACP1000 reactor from CNNC and after completing the review granted a construction licence, for the CNNC version of Hualong One, 1161 MWe gross.
In April 2015 China Nuclear Engineering & Construction Group Co (CNEC) won the tender for civil engineering construction and installation work for the conventional island of the plant, which it said would use Hualong One reactors. The associated China Zhongyuan Engineering Corporation (CZEC) became the general contractor. Construction of the first unit started in August 2015 with little fanfare and is expected to take 72 months (52 months for conventional island). Construction of the second unit started at the end of May 2016, according to IAEA, but without any announcement or notification on the PAEC website.
In the light of its inability to buy uranium on the open market, PAEC says that Pakistan has agreed with CNNC to provide lifetime fuel supply for the reactors, this being specified as 60 years.
Nuclear Power Reactors Under Construction
Reactor Province Type MWe gross Construction start Planned commercial operation
Chashma 4 Punjab CNP-300 340 Dec 2011 October 2017
Karachi 2 (Coastal) Sindh Hualong One 1161 Aug 2015 late 2021
Karachi 3 (Coastal) Sindh Hualong One 1161 May 2016 late 2022
Total (3) 2662
Karachi Coastal is also known as K2 & K3, or KANUPP 2&3

Nuclear Power Plants
.. Mr. Stone presents the Pinstech (Pakistan Institute of Nuclear Science &Technology) model to President Ayub Khan, November 1961 Pinstech Nuclear Reactor Islamabad 1965.
defence.pk
Operating Reactors in Pakistan
Reactor Province Type MWe net Construction start Commercial operation Planned close
Karachi 1 Sindh PHWR 125 1966 December 1972 2019
Chashma 1 Punjab PWR 300 1993 June 2000 2040
Chashma 2 Punjab PWR 300 2005 May 2011 2051
Chashma 3 Punjab PWE 315 May 2011 December 2016 2056
Total (4) 1040 operating
Karachi is also known as KANUPP, Chashma as CHASNUPP.
Enriched fuel for the PWRs is imported from China.
The 2005 Energy Security Plan included intention of lifting nuclear capacity to 8800 MWe, 900 MWe of this by 2015 and a further 1500 MWe by 2020. Projections included four further Chinese reactors of 300 MWe each and seven of 1000 MWe, all PWR. There were tentative plans for China to build two 1000 MWe PWR units at Karachi as KANUPP 2&3, but China then in 2007 deferred development of its CNP-1000 type which would have been the only one of that size able to be exported. Pakistan then turned its attention to building smaller units with higher local content. However, in 2013 China revived its 1000 MWe designs with export intent, and made overtures to Pakistan for the ACP1000 design, which became Hualong One – see below.
Chashma 3 and 4
In June 2008 the government announced plans to build units 3&4 at Chashma, each 320 MWe gross and largely financed by China. A further agreement for China's help with the project was signed in October 2008, and given prominence as a counter to the US-India agreement shortly preceding it.
In March 2009 China's SNERDI announced that it was proceeding with design of Chashma 3&4, with China Zhongyuan Engineering Corp (CZEC) as the general contractor and China Nuclear Industry No.5 Construction Company as installer. In April 2009, a design contract with SNERDI was signed, and the government said that it had approved the project at a cost of $2.37 billion, with $1.75 billion of this involving "a foreign exchange component". In March 2010 Pakistan announced that it had agreed the terms for Chashma 3&4, whereby China would provide 82% of the total US$ 1.912 billion financing as three 20-year low-interest loans. It would also provide fuel for the reactors’ lifetime nominally of 40 years.
The main construction contract was signed in June 2010, and the two 340 MWe CNP-300 (315 MWe net) units were to be completed in eight years. They will have a design life of 40 years and be under IAEA safeguards. Construction of unit 3 officially started at the end of May 2011, and unit 4 in December 2011. Early in 2014 PAEC said they were several months ahead of schedule. In 2015 CZEC said completion of unit 3 would be in 2016, and in fact it was grid-connected in October, with full power and commercial operation in December. Unit 4 is expected to be grid connected by mid-2017.
The Nuclear Suppliers Group (NSG) has raised some questions about China's supply of Chasma 3&4. Contracts for units 1&2 were signed in 1990 and 2000 respectively, before 2004 when China joined the NSG, which maintains an embargo on sales of nuclear equipment to Pakistan. China argued that units 3&4 are similarly "grandfathered", and arrangements are consistent with those for units 1&2.
Chashma 5
In November 2010 the PAEC is reported to have signed a construction agreement with China National Nuclear Corporation (CNNC) for a fifth unit at Chashma. In February 2013 a further agreement was signed by PAEC with CNNC for a 1000 MWe unit at Chashma. It was reported that China expected that this deal would be controversial under the NPT and guidelines of the NSG. Early in 2013 CNNC confirmed its intention to build a 1000 MWe class reactor, and said it would be an ACP1000 unit, though not necessarily at Chashma. The status of any continuing plan for Chashma 5 is very uncertain, and it may have been displaced by plans for a plant near Multan in southwest Punjab. Certainly it has been overtaken by the Karachi Coastal project.
Karachi Coastal power project, K2 and K3
In June 2013 the Planning Commission said that two CNNC 1000 MWe class reactors would be used for Karachi 2 and 3 (KANUPP 2&3) near Karachi unit 1. Two coastal sites had been under consideration for the twin 1100 MWe units. CNNC in April 2013 announced an export agreement for the ACP1000, nominally 1100 MWe, apparently for Pakistan. This was confirmed in June by the PAEC which said that the next nuclear project would be 1100 MWe class units which it would build, the Karachi Coastal Power station.
In July 2013 ECNEC approved two units of the Karachi Costal Power Project with net generation capacity of 2,117 MWe. The total cost of this was estimated at Rs 959 billion ($9.595 billion), with $6.5 billion (68%) being vendor finance. PAEC also said that 82% of the total cost would be financed by China. At the end of August 2013 contracts were signed in Shanghai with CNNC, China Zhongyuan Engineering Co. Ltd. (CZEC), China Nuclear Power Engineering Co. Ltd. (CNPE), Nuclear Power Institute of China (NPIC), and East China Electric Power Designing Institute (ECEPDI). Ground breaking at the site near Paradise Point, 25 km west of Karachi, took place in November 2013, but in October 2014 the Sindh high court ruling stopped site work following a challenge on environmental grounds, and the restraining order was extended to early December. The project was re-launched in August 2015, and construction of the first unit started then.
The Pakistan Nuclear Regulatory Authority received the safety analysis of China’s ACP1000 reactor from CNNC and after completing the review granted a construction licence, for the CNNC version of Hualong One, 1161 MWe gross.
In April 2015 China Nuclear Engineering & Construction Group Co (CNEC) won the tender for civil engineering construction and installation work for the conventional island of the plant, which it said would use Hualong One reactors. The associated China Zhongyuan Engineering Corporation (CZEC) became the general contractor. Construction of the first unit started in August 2015 with little fanfare and is expected to take 72 months (52 months for conventional island). Construction of the second unit started at the end of May 2016, according to IAEA, but without any announcement or notification on the PAEC website.
In the light of its inability to buy uranium on the open market, PAEC says that Pakistan has agreed with CNNC to provide lifetime fuel supply for the reactors, this being specified as 60 years.
Nuclear Power Reactors Under Construction
Reactor Province Type MWe gross Construction start Planned commercial operation
Chashma 4 Punjab CNP-300 340 Dec 2011 October 2017
Karachi 2 (Coastal) Sindh Hualong One 1161 Aug 2015 late 2021
Karachi 3 (Coastal) Sindh Hualong One 1161 May 2016 late 2022
Total (3) 2662
Karachi Coastal is also known as K2 & K3, or KANUPP 2&3