K4 Project
Project 64% complete, work continues on all important sites, 86 billion rupees has been spent so far.
Chairman WAPDA Lieutenant General Muhammad Saeed (Retired) visited the project, inspected the construction work.
Chairman WAPDA Lieutenant General Muhammad Saeed (Retd) paid a two-day visit to Greater Karachi Bulk Water Supply Scheme (K4 Project) and inspected the construction work at the main sites of the project. Among the mentioned sites, there are an under-construction intake structure and two pumping stations on Kenjhar Lake located in District Thatta, Kenjhar.
There are major construction sites on water transfer system consisting of high-pressure pipelines from the lake to Karachi and an under-construction filtrish plant in Karachi. It is noteworthy that the federal government has commissioned WAPDA to meet the water needs in Karachi city. He was assigned the responsibility of constructing the four project.
General Manager and Project Director briefed Chairman Wapda along with Consultants and Contractors on each contract package completed so far, future targets and schedule of completion. K4 Project for faster completion. Co has been divided into eight different contract packages, and construction work is underway on major sites of all packages.
The project is 64% completed and has been spent on Rs 86 billion so far. If the necessary funds are allocated, WAPDA will plan this project. May complete during 2026. Financial progress and future financial needs were also discussed during the briefing.
Mentioning the importance of the K4 project for Karachi city, Chairman WAPDA urged contractors to accelerate construction work by ensuring availability of additional resources so that construction targets can be achieved on time. He emphasized that the pipe Specific work on the contract package of Line 2 needs to be accelerated. Chairman instructed the project team to maintain close and effective contact with the Sindh government during the construction of the project. He expressed hope that the provincial government will distribute water in Karachi city. K will complete the plan to expand the system as soon as possible to fully benefit from the K4 project.
The K4 project has been designed to provide Karachi city with 650 million gallons of water per day. The project will be completed in two phases. Currently, WAPDA is working on the first phase of the K4 project, which will provide Karachi with 260 million gallons of daily water upon completion. Karachi will be able to provide 390 million gallons of water daily when the second phase of the K4 project is constructed.
Earlier, Chairman WAPDA also visited all worksites of the Nai Gaj Dam Project in District Dadu, Sindh. The purpose of his visit was to assess the situation at the project site and to set out a schedule for resuming construction work on the project, which There is a disruption from February 2025, due to several reasons. These reasons include the contractor's return to court, extremely slow pace of construction work in the past and financial issues. General Manager Projects South Wapda, Project Director and Consultants were also present at the visit of Chairman Wapda. تھے۔
28 thousand 800 acres of barren land will be cultivated upon completion of the Nai Gaj Dam project. Thanks to the project, the locals will get 4
Decimal 2 MW cheapness electricity will also be provided.
'WAPDA to Complete K-IV Project During 2026 Subject to Availability of Funds'
November 29, 2025: Chairman WAPDA Lt Gen Muhammad Saeed (Retd), during a two-day visit, reviewed in detail the construction progress on key sites of Greater Karachi Bulk Water Supply Scheme (K-IV Project) being constructed by WAPDA on behalf of the Federal Government to cater for water needs of Karachi - economic hub and the largest city of the country.
The key work fronts visited by the Chairman included intake structure and pumping stations at Keenjhar Lack in district Thatta, water conveyance system comprising high-pressurised pipelines from Keenjhar Lack to Karachi and one of the filtration plants at Karachi.
During the visit, the General Manager and Project Director along with the Contractors and the Consultants briefed the Chairman about site as well as contract-wise progress, key targets and their completion schedules. K-IV Project has been divided in eight contract packages for its completion on fast-track basis. At present, construction work is in progress on all key sites of these contract packages. The overall physical progress on the Project is 64 percent with a spending of Rs. 86 billion. WAPDA stands committed to completing the K-IV during 2026 provided the funds are made available accordingly. The briefing also encompassed current financial status and funding requirements for the Project in the days to come.
The Chairman, highlighting the critical significance of the Project for Karachi, urged upon the Contractors to expedite the pace of work by deploying additional resources to match the timelines. The Contractor, working on Pipeline-2 (PL-2), in particular, needs to catch-up the construction schedule of the respective contract package. The Chairman directed the Project Team to be in close liaison with Government of Sindh for smooth implementation of the Project. He expressed hope, the Provincial Government will complete Water Distribution/Augmentation Project in time, so that benefits of the K-IV could be fully accrued.
K-IV Project envisages to provide 650 million gallon per day (MGD) water to Karachi from Keenjhar Lake. The Project is planned to be completed in two phases. At present, WAPDA is constructing Phase-I of the Project for supplying 260 MGD water to Karachi. The subsequent phases, when implemented, will add another 390 MGD water to the system.
