Official! Rp 2.7 Trillion Pipeline Project Begins First Gas Flow
18 March 2026
Batang Industrial Park, Central Java, one of industrial parks in Java that will get the gas supply from the project
Batang — Indonesia’s Ministry of Energy and Mineral Resources (ESDM) has officially commenced first gas flow (gas-in) for the Cirebon–Semarang (Cisem) Phase II natural gas transmission pipeline project.
The project, valued at Rp 2.7 trillion, marks a significant step in strengthening national energy security while supporting industrial growth.
The inauguration was carried out by Deputy Minister of Energy and Mineral Resources Yuliot Tanjung on Wednesday (March 18, 2026), following the completion of all Engineering, Procurement, and Construction (EPC) works on March 5, 2026, as formalized through the signing of the project handover document (BAST-1).
Yuliot emphasized that the Cisem Phase II project is part of the government’s strategic agenda to achieve energy independence. He added that the infrastructure is expected to accelerate the development of industrial zones, commercial areas, and new economic growth centers across Java.
“The availability of energy will further accelerate growth in regions connected by this critical infrastructure,” Yuliot said during the event in Batang.
Lower Costs, Stronger Industrial Competitiveness
Yuliot also highlighted that the project’s state budget (APBN)-based financing model plays a key role in maintaining industrial competitiveness. Direct government investment helps reduce gas transportation costs (toll fees), enabling more competitive gas prices for industrial users.Operational Readiness Confirmed
At the same event, Director General of Oil and Gas Laode Sulaiman confirmed that the pipeline is fully operational following a series of technical tests, including leak testing.According to him, the results showed no leakage, indicating that the pipeline is ready to distribute gas to consumers, particularly in western Java.
He also noted that several users have already expressed initial commitments to utilize the pipeline, including:“The tests confirmed there are no leaks, and the pipeline is ready to operate. We will soon begin supplying gas to consumers in western Java,” Laode stated.
- Balongan Refinery
- PT Cikarang Listrindo
- Other industrial customers
“All technical aspects have been completed. The contractor and construction management teams have performed well,” he added.
Project Overview
- Length: ~242 kilometers
- Status: National Strategic Project (PSN)
- Construction period: August 6, 2024 – March 5, 2026
- Total safe working hours: 4.65 million hours
- Peak workforce: 1,981 workers
- Local content (TKDN): 60.58%
Pertamina Jambaran Tiung Biru, East Java, the source of gas of the pipe lines
Future Operations
The management of the Cisem Phase II pipeline has been assigned to LEMIGAS under Ministerial Decree No. 125.K/MG.01/MEM.M/2026. Going forward, LEMIGAS will collaborate with partners to optimize the utilization of the asset.Gas supply for the pipeline will be sourced from the Jambaran Tiung Biru (JTB) gas field.
Sah! Proyek Pipa Rp 2,7 Trilliun Ini Resmi Mengalirkan Gas Perdana
Kemenetrian ESDM resmi mengalirkan gas perdana (gas-in) pada proyek Pipa Transmisi Gas Bumi ruas Cirebon-Semarang (Cisem) Tahap II.
www.cnbcindonesia.com
Sah! Proyek Pipa Rp 2,7 Trilliun Ini Resmi Mengalirkan Gas Perdana
Kemenetrian ESDM resmi mengalirkan gas perdana (gas-in) pada proyek Pipa Transmisi Gas Bumi ruas Cirebon-Semarang (Cisem) Tahap II.