Construction work is continuing on Greater Karachi Bulk Water Supply Scheme (K-IV Project). The project envisages to supply 650 million gallon water per day (MGD) to Karachi from Keenjhar Lake.

WAPDA has been entrusted by the Federal Government to construct Phase-I of the project, which will provide 260 MGD water to Karachi.

1705072395352.png
 
Last edited:
K-IV Project to provide 650 million gallon per day (MGD) water to Karachi from Keenjhar lake.
The Project will be completed in two phases.
At present, WAPDA is constructing Phase-I, which is scheduled for completion in October 2024. Construction activities are continuing on all eight sites of the Project.
Phase-I will supply 260 MGD to Karachi.
PC-I cost of the Phase-I is Rs 126 billion, expenditure till date is Rs.40 billion and accumulative progress of 40% has been achieved.

Credit ,,, WAPDA


1705072484704.png



1705072502846.png



1705072522001.png
 
Construction work is in progress on various sites of Greater Karachi Bulk Water Supply Scheme K-IV. Completion of the Project is planned in two phases to supply 650 million gallon water per day #Karachi from Keenjhar Lake. Phase-I will provide 260 MGD water to Karachi.

Image
Image
Image



Image



To view this content we will need your consent to set third party cookies.
For more detailed information, see our cookies page.
 
Last edited:
Sir images are not visible
Indus Hospital & Health Network, Korangi campus in Karachi is expanding from a 300-bed tertiary hospital to a 1300+ bed teaching hospital to cater to the growing need for free health services. Additionally, a new hospital is also under construction in Lahore, which will cater to 600 beds in phase 1.

Make the expansion project a reality!

1709650092259.png


 
The open urban spaces being developed in Karachi.
Photos are of the ones developed in Malir & inaugurated yesterday.


Image


Image


Image
 

WAPDA

April 15, 2024

Latest pics of construction work at various sites of K-IV Project, planned to be completed in two phases to supply 650 million gallon water per day (MGD) to Karachi from Keenjhar Lake. The phase-I to provide 260 MGD water.










438712322_968593467970261_1070330611110912474_n.jpg
 
KARACHI: Under-construction Greater Karachi Bulk Water Supply Scheme (K-IV Project). It envisages to provide 650 million gallon per day (MGD) to Karachi from Keenjhar Lake. Phase-I of K-IV will supply 260 MGD.

1715091897668.png
 

CSCEC, EMAAR Pakistan Sign Landmark Contract for Construction of High-End Park Edge Project in Karachi​

Gwadar Pro
May 11, 2024

KARACHI- China State Construction Engineering Corporation Limited (CSCEC) signed a landmark contract on May 8 with EMAAR Pakistan to construct a high-end Park Edge residential project in Karachi. This collaboration aims to elevate local residential quality and provide modern living facilities to the residents of Karachi.

Located at the heart of Pakistan's largest city, Karachi, the Park Edge project is a cutting-edge residential development that will set new standards in smart building. With a total floor area of 208,700 square meters, the complex will be developed by EMAAR Pakistan, a subsidiary of Dubai-based EMAAR Properties, and constructed by CSCEC, a leading Chinese construction giant.

The project will feature twin towers of 43-storeys with a height of 152 metres. These high-end residential towers will incorporate smart building systems to provide comfort, safety and convenience for residents. The business district in a skirt building, meanwhile, houses ancillary commercial facilities and fitness amenities.

The Park Edge project is expected to be a major addition to the Karachi skyline, providing residents with brand new living spaces and world-class amenities. It is also expected to boost the local economy by creating job opportunities and attracting vast investments throughout the country in the property sector.

So far, CSCEC has delivered several landmark projects in Pakistan including the passenger terminal building of Islamabad International Airport, Centaurus mixed-use development in Islamabad, Arfa Kareem IT Tower in Lahore, PKM motorway and JF-17 technical buildings in Kamra.
 
Under Construction Malir Expressway, Karachi.













441925878_837535431736557_1870334807462021897_n.jpg
 
Progress at under-construction Greater Karachi Bulk Water Supply Scheme-KIV Project

Stage-1: 260 Million Gallon per Day (MGD) water supply to Karachi
Stage-2: 390 MGD
Total: 650 MGD water supply to Karachi


1717884830481.png


1717884857902.png
 