Energy Sectors / Industries / Projects

Chinese company installs world-first 765 kV auto-transformer at Mansehra substation​

By Tahir Ali | Gwadar Pro
Apr 23, 2026
1777037796972.png

ISLAMABAD- A world-first 765 kV auto-transformer featuring constant-flux voltage regulation has been installed at the Mansehra Substation Project by POWERCHINA, marking a significant milestone in Pakistan’s power transmission development.

According to POWERCHINA statement issued on Thursday, the weighing 225 tonnes, the single-phase, auto-coupled transformer is equipped with an on-load tap-changing system and a three-stage cooling mechanism. It sets a new benchmark among AC transformers of its class, achieving both the highest step-voltage and the widest tap range.

The installation fills a key technological gap in Pakistan’s 765 kV extra-high voltage (EHV) transmission sector and signals that the country’s first substation operating at this voltage level has entered the core equipment installation phase.

Project officials said the development will strengthen grid stability and help address regional electricity shortages once the substation becomes operational.

The Mansehra project is part of Pakistan’s broader efforts to modernize its transmission infrastructure and improve energy efficiency. The next phase will involve installing six additional main transformers, which is expected to further accelerate progress and support optimization of the country’s energy mix.

Upon completion, the substation is expected to play a vital role in enhancing power reliability and supporting long-term economic growth.
 
To view this content we will need your consent to set third party cookies.
For more detailed information, see our cookies page.
 

Hydropower generation reaches 6,000MW: PD

April 30, 2026

ISLAMABAD: Power generation from hydropower sources reached 6,000MW during peak hours on Tuesday night against a total installed hydel capacity of 11,500MW.

According to Power Division, electricity generation improved further due to the supply of local gas to certain power plants. Increased hydropower generation, along with the availability of additional indigenous gas, contributed to enhanced stability in the national grid, particularly through supply from the southern region of the country.

This improvement facilitated the addition of another 100MW to the system.

According to the Power Division, a total of 500MW was transmitted from the southern region to the national grid.

The spokesperson said that distribution companies carried out load management ranging from 25 minutes to one hour during peak hours last night. However, after 8:00pm, no load management was carried out as electricity demand declined due to improved weather conditions.
 

12 IPPs of 2,577MW set to retire in 10 years: PD


ISLAMABAD: The Ministry of Energy (Power Division) has stated that 12 Independent Power Producers (IPPs), with a combined capacity of 2,577 MW, are scheduled to retire over the next 10 years.

According to the Power Division, IPP contracts are structured based on commissioning dates and system requirements, making it neither technically feasible nor commercially viable to terminate all agreements simultaneously. These contracts are typically reviewed upon completion of their agreed tenure.

The ministry explained that while some projects are retired at the end of their lifecycle, others may have their contracts extended or renewed to ensure grid stability, meet capacity requirements, and address strategic considerations such as frequency control and overall system reliability.
 
As per the official details, several plants operating under the National Grid Company (NGC) system are set to retire over the coming years.

These include: KAPCO (495 MW, RLNG) in 2029; Liberty Power (235 MW, gas) in 2028; Kohinoor Energy (131 MW, RFO) in 2028; Fauji Kabirwala Power Company (157 MW, RLNG) in 2032; Uch Power (586 MW, gas) in 2031; Altern Energy Limited (31 MW, RLNG) in 2032; Attock Gen Limited (163 MW, RFO) in 2034; Gul Ahmed Energy Limited (136 MW, RFO) in 2025; and Engro Powergen Qadirpur (223 MW, gas) in 2035.
 
The government has approved the supply of up to 40 million cubic feet per day (MMCFD) of gas to National Steel Complex Ltd (NSCL), formerly Tuwairqi Steel Mills Ltd (TSML), paving the way for the revival of the long-idled steel project after years of disputes and failed international arbitration against Pakistan, Business Recorder reported, citing sources close to the petroleum minister.


Sources said that the Economic Coordination Committee (ECC) recently approved a summary submitted by the Petroleum Division allowing Sui Southern Gas Company Limited (SSGCL) to provide gas for industrial processing and captive power generation at notified industrial tariffs, subject to availability.


The ECC decision will now be placed before the Federal Cabinet for ratification.

TSML was established in January 2013 with an annual production capacity of 1.28 million tonnes and was jointly financed by Al-Tuwairqi Holdings of Saudi Arabia and South Korea’s POSCO.

The plant was based on Direct Reduced Iron (DRI) technology using the MIDREX process owned by Kobe Steel of Japan, which relies heavily on natural gas as feedstock.

The government had originally allocated gas to the project in 2005, while SSGCL signed a Gas Sales Agreement in August 2006 for supply of 45 MMCFD gas, including 40 MMCFD for industrial processing and 5 MMCFD for captive power generation.


However, after starting operations in January 2013, the plant shut down within months after seeking gas supply at subsidised fertiliser feedstock tariffs instead of industrial tariffs applicable to the project.

At the time, industrial gas tariffs stood at ₨488 per MMBtu compared to fertiliser feedstock tariffs of ₨123 per MMBtu. Officials estimated that provision of subsidised gas would have caused around ₨5 billion in revenue losses to SSGCL through cross-subsidisation.

The initial gas agreement expired in 2016 without renewal, while the original gas allocation also lapsed.

In 2018, Saudi sponsors initiated arbitration proceedings against Pakistan at the Permanent Court of Arbitration in The Hague, seeking $500 million in damages under Organisation of Islamic Cooperation investment agreements.

The tribunal ruled in favour of Pakistan in December 2023, dismissing all claims and directing claimants to bear legal and administrative costs.


Meanwhile, management control of the steel plant shifted to United States-based Ciena Group in April 2022, after which the company was renamed National Steel Complex Ltd.


The project’s revival later came under consideration at the Special Investment Facilitation Council (SIFC).

During multiple Executive Committee meetings between 2023 and 2024, Petroleum Division was directed to explore gas allocation options of up to 50 MMCFD for revival of steel production.

According to sources, SSGCL was later instructed to issue a bankable commitment letter for the supply of 45 MMCFD gas at standard industrial tariffs for an initial period of 10 years, extendable by another decade.

SSGCL issued the commitment letter in November 2025, confirming system capacity for gas supply at Oil and Gas Regulatory Authority-notified tariffs, subject to approvals.

Officials stated that ECC had earlier revised the natural gas allocation priority framework in September 2024, placing industrial process gas alongside domestic and commercial sectors in the highest priority category.


Under the revised framework, NSCL qualified for gas supply as a major industrial project.

The Petroleum Division subsequently proposed allocation of up to 40 MMCFD gas for industrial processing and captive power generation at applicable industrial tariffs and levies, while directing both parties to finalise terms of the Gas Sales Agreement based on approved volumes.
 
In 2018, Saudi sponsors initiated arbitration proceedings against Pakistan at the Permanent Court of Arbitration in The Hague, seeking $500 million in damages under Organisation of Islamic Cooperation investment agreements.

The tribunal ruled in favour of Pakistan in December 2023, dismissing all claims and directing claimants to bear legal and administrative costs.


Meanwhile, management control of the steel plant shifted to United States-based Ciena Group in April 2022, after which the company was renamed National Steel Complex Ltd.

So Saudi fund lost $500m investment because they didn't get subsidized gas rates and lost the case in international court LOL
 

Nepra approves tariff for electricity import from Iran

May 15, 2026

ISLAMABAD: The National Electric Power Regulatory Authority (NEPRA) has approved tariff with the range of 12.40 Cents/kWh for import of 104 MW electricity and an additional 100 MW from Iran’s state-owned power company, TAVANIR, while expressing serious concerns over procedural violations and lack of long-term planning by Pakistani authorities.

The decision comes in response to an application filed by the Central Power Purchasing Agency-Guarantee Limited (CPPA-G), following the Economic Coordination Committee’s (ECC) approval in August 2023 to extend and expand the cross-border electricity supply agreement.

The CPPA-G had sought approval for extending the tariff of the existing 104 MW supply and securing an additional 100 MW through amendments to the long-standing power purchase agreement with Iran.
 

Users who are viewing this thread

Country Watch Latest

Latest Posts

Back
Top