I think every dam or big project in Pakistan is always behind schedule. I think the reasons are inefficiencies, mismanagement plus corruption. At this point I am just content that something is being slowly built.It seems that this project is seriously behind schedule
Even for that we need cheaper alternativesSo Mohmand dam, will generate 2.8bn units/year and cost $2.5bn. I hope the storage/flood protection/agriculture part is worth it because electricity from dams no longer make economic sense.